Client

CBRE

Location

Grafton Gate

Budget

£3,600,000

Duration

20 weeks

Download Case study

At Grafton Gate we had been re-approached by CBRE due to our successful completion of Pembroke Court. We were to carry out a major plant replacement on 4 floors of office fit-out in helping reduce the carbon imprint for their repeat client Picton. For these works we carried out site visits and ascertained scope requirements and the most commercially viable solution.

Mectric acted as the main contractor in the removal of 1No. Chiller 4No. Modular boilers and the complete strip out of the LTHW and CHW services. This included the installation of a complete new VRF system within an occupied building.

Related Projects

mectric solutions logo
Privacy Overview

This website uses cookies so that we can provide you with the best user experience possible. Cookie information is stored in your browser and performs functions such as recognising you when you return to our website and helping our team to understand which sections of the website you find most interesting and useful.